Last Update By |
Inspectors Notes |
Chargeable Failure |
Affects HFR |
Booth, Russell |
Looked at C3 Shell 1st, 2nd and 3rd floor corridors electrical AC/RF
Advantage
1) Romex cabling, boxes and supports in walls and ceilings
2) Partial Approval: Corridor C2/C3 connectors need to be inspected when ready
3) Inspection does not include stairwells, common areas, electrical/mechanical rooms, IDF closets and corridor connectors
4) 1st floor: Corridor from C2 connector to egress at parking deck gate
5) 2nd Floor: Corridor from C2 connector to last unit before walking bridge, No inspection on 2nd floor walking bridge to stairwell at parking deck
6) 3rd floor: Corridor from C2 connector to stairwell at parking deck ...Ok |
|
0 |
Booth, Russell |
Looked at C3 Shell 1st, 2nd and 3rd floor corridors electrical AC/RF
Advantage
1) Romex cabling, boxes and supports in walls and ceilings
2) Partial Approval: Corridor C2/C3 connectors need to be inspected when ready
3) Inspection does not include stairwells, common areas, electrical/mechanical rooms, IDF closets and corridor connectors
4) 1st floor: Corridor from C2 connector to egress at parking deck gate
5) 2nd Floor: Corridor from C2 connector to last unit before walking bridge, No inspection on 2nd floor walking bridge to stairwell at parking deck
6) 3rd floor: Corridor from C2 connector to stairwell at parking deck ...Ok |
|
0 |
|
|
|
|
|
|
|
|
|
|
|
|
|