Last Update By |
Inspectors Notes |
Chargeable Failure |
Affects HFR |
Koprivica, Milan |
installed shaft liner lid for inspect #3.
Also talked to Lonny concerning doors at A3 - 45 minute fire door with glazing pending testing submittal per NFPA 80 of both glazing and door.
And doors at 3 hour fire wall A3 - 03 series, 46 series, and ST1 series require 180 minute ratings for a 3 hour firewall, not 90 minute and labelled or on plans.
And relocation of signage at interior stairs indicating floor level, roof access, level to exit discharge - acceptable locations interior stair for building/fire department.
Also location of roof hatch access and rail requirements openings within 10'.
|
|
0 |
Koprivica, Milan |
installed shaft liner lid for inspect #3.
Also talked to Lonny concerning doors at A3 - 45 minute fire door with glazing pending testing submittal per NFPA 80 of both glazing and door.
And doors at 3 hour fire wall A3 - 03 series, 46 series, and ST1 series require 180 minute ratings for a 3 hour firewall, not 90 minute and labelled or on plans.
And relocation of signage at interior stairs indicating floor level, roof access, level to exit discharge - acceptable locations interior stair for building/fire department.
Also location of roof hatch access and rail requirements openings within 10'.
|
|
0 |
|
|
|
|
|
|
|
|
|
|
|
|
|