Inspection Results
Confirmation # 3402742011
Received Date Oct 9, 2018
Requested Date Oct 10, 2018
Result Date Oct 10, 2018
Result Overall Failed
Inspector Moran, Patrick
Is RDP Inspection
LiveRemoteInspection
 
Task Requested SL - Slab
Result 02 - Failed
Task Defect Code Defect Description Defect Note
SL 114 Vapor barrier installation The inspected task was either incomplete, installed incorrectly, missing, or not per plan.
SL 115 Wire mech installation The inspected task was either incomplete, installed incorrectly, missing, or not per plan.
SL 119 Steel not properly installed
Screen ID: 467227